Element unit rate
The New Rules of Measurement (NRM) are published by the Royal Institute of Chartered Surveyors (RICS). They provide a standard set of measurement rules for estimating, cost planning, procurement and whole-life costing for construction projects.
According to NRM1: Order of cost estimating and cost planning for capital building work, the term 'element' refers to:
'...a major part of a group element (e.g. the elements that create group element 3:
Internal finishes are 3.1: Wall finishes, 3.2: Floor finishes, and 3.3: Ceiling finishes).'
The term ‘element unit rate’ (EUR) means:
‘…the total cost of an element divided by the element unit quantity (EUQ). For example, the EUR for external walls is the total cost of the external walls divided by EUQ for external walls. EURs include all the cost of all materials, labour, plant, subcontractor’s preliminaries, subcontractor’s design fees and subcontractor’s overheads and profit. EURs exclude main contractor’s preliminaries, main contractor’s overheads and profit and other allowances, such as project/design team fees, other development/project costs, risk allowances and inflation. These items are to be assessed separately.’
Where, the ‘element unit quantity’ (EUQ) is:
‘…a unit of measurement that relates solely to the quantity of the element or sub-element itself (e.g. the area of the external walls, the area of windows and external doors and the number of internal doors).’
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
What they are, how they work and why they are popular in many countries.
Plastic, recycling and its symbol
Student competition winning, M.C.Esher inspired Möbius strip design symbolising continuity within a finite entity.
Do you take the lead in a circular construction economy?
Help us develop and expand this wiki as a resource for academia and industry alike.
Warm Homes Plan Workforce Taskforce
Risks of undermining UK’s energy transition due to lack of electrotechnical industry representation, says ECA.
Cost Optimal Domestic Electrification CODE
Modelling retrofits only on costs that directly impact the consumer: upfront cost of equipment, energy costs and maintenance costs.
The Warm Homes Plan details released
What's new and what is not, with industry reactions.
Could AI and VR cause an increase the value of heritage?
The Orange book: 2026 Amendment 4 to BS 7671:2018
ECA welcomes IET and BSI content sign off.
How neural technologies could transform the design future
Enhancing legacy parametric engines, offering novel ways to explore solutions and generate geometry.
Key AI related terms to be aware of
With explanations from the UK government and other bodies.
From QS to further education teacher
Applying real world skills with the next generation.
A guide on how children can use LEGO to mirror real engineering processes.
Data infrastructure for next-generation materials science
Research Data Express to automate data processing and create AI-ready datasets for materials research.
Wired for the Future with ECA; powering skills and progress
ECA South Wales Business Day 2025, a day to remember.
AI for the conservation professional
A level of sophistication previously reserved for science fiction.
Biomass harvested in cycles of less than ten years.
An interview with the new CIAT President
Usman Yaqub BSc (Hons) PCIAT MFPWS.
Cost benefit model report of building safety regime in Wales
Proposed policy option costs for design and construction stage of the new building safety regime in Wales.
Do you receive our free biweekly newsletter?
If not you can sign up to receive it in your mailbox here.